-concreting of 2 pilecaps
-concreting of stumps & tie beams
-excavation of 1 pilecap pit
-installation of 2 pilecaps reinforcement cages & stumps rein'ft
-bricklaying activities continue at 3rd floor ( main block)
-top windows installation @ pra-sekolah continue
-installation and casting of stiffeners at balcony(main block)
-stiffening of soil/backfill at Pentas area.
-anti-termite activities at ground slab area & pile caps pit